Old Coulee Road Section 2

HLT, Construction started construction on June 11, 2018.  This project will consist of widening and safety enhancing the existing subgrade to include extending or replacing existing drainage facilities, resurface with crushed surfacing, slope work, removing fence and other incidental work as required.  They have 60 working days to complete the work.  60 working days will be at the beginning of September.

8.29.2018- Currently closed to ALL traffic.

The road will be closed to thru traffic from M.P. 8.07 to M.P. 12.15, (250’ South of the Bagdad intersection).  Please use Highway 174 and Douglas Road for an alternative route.  People with property adjacent to the project will be allowed within the construction limits.  All other are directed to use the dedicated detour route.

Preconstruction Photos-

Video shot by Lincoln County Commissioner Rob Coffman of the Old Coulee Work.