NOTICE FOR PUBLIC REVIEW OF
LINCOLN COUNTY PASSIVE REHYDRATION PREFEASIBILITY REPORT
Comments due January 31st, 2011
The Lincoln County Conservation District has completed the Pre-Feasibility
Assessment for the proposed
Lincoln County Passive Rehydration Project. The Prefeasibility Assessment was
completed in order to
determine if any fatal flaws were identified that would prohibit the further
evaluation of diverting water from Lake
Roosevelt and conveying it to the tributary drainages of Crab Creek. Initial
review has determined that a
recommendation to proceed to the Feasibility Study and Pilot Testing Program
should be conducted in 2011.
The Prefeasibility Assessment also ranked potential drainages in which to
conduct a Pilot Testing Program, of
which the Lake Creek Drainage was selected.
The LCCD is seeking public comment on the Draft Prefeasibility Report. Comments
will be received by the
LCCD through January 31st, 2011. The Draft Report and comment forms are
available and attached above.
Hard copies and CD’s of the report are also available at the LCCD office in
Davenport, WA, or by contacting
Dave Lundgren, LCCD Manager at: 509-725-4181, ext. 3. The LCCD believes
stakeholder input is an important
part of the success of this project and we encourage you to please review the
report and provide any comments.
For information, please call:
David Lundgren, District Manager
Lincoln County Conservation District
1310 Morgan Street
Davenport, WA 99122
Gene St.Godard with WNR Group
PO Box 28755, Spokane, WA 99228